Taking Over or Completion CertificateFundamentals
The most important part of a project is Handing over the Works to the Client
| Hudson Formula and Extension of Time Claims
The payment of additional monies in respect of Head Office overheads and profit
| |||
Once ready for hand over the Site Manager should submit his notice in writing to the Engineer with a copy to the Employer. The Engineer must issue a Taking Over Certificate if... | more | is the subject of much debate and discussion. The Hudson's formula is generally accepted as a recognised method for calculating the additional cost payable for head office overheads... | more | |||
PC Sums and Provisional Sums Clarified
In Construction the term PC sum is often confused with Provisional Sum. Whilst both terms are
| Tracking delay events:
Tracking and keeping your contractual notices valid, that is submitted every 28days
| |||
associated to allowances being made for a specific activity or item, there are distinct differences in these two terms. PC Sums are normally associated with an average cost of a specific item whereas Provisional Sums are estimated allowances... | more | can become quite a tricky task if many events at various times are registered. A valid notice shall be in writing on a company letterhead addressed to the Engineer with a copy to the Employer... | more | |||
Labour Costing
Labour productivity is fundamental to the success of any Construction project. Completing this exercise
| Pricing Preliminaries
Preliminaries and General by virtue of its scope and broad definition can easily contribute or result in
| |||
on a daily basis will be extremely helpful in managing the project delivery and will also provide a good understanding where losses are incurred. This could identify opportunities to recover expenses in a variation claim... | more | huge losses if not correctly understood or determined at the tender stage. Pricing of preliminaries starts with your site establishment, methodology of construction, access restrictions and programme requirements... | more |
Pricing Concrete Formwork and Reinforcing
Pricing these rates can be a complicated exercise.
| Dayworks in the Construction Industry
Daywork is work for which the contractor is paid on the basis of actual Cost plus an agreed %
| |||
However, by using a well designed template for this purpose will not only ensure correct calculation but also clarify the method of construction and restrictions to be considered...| more | Dayworks are bound to come up from time to time since it is impossible working from a Bill of Quantities to cover all eventualities. There two options how Daywork rates can be priced in the bill...| more | |||
Prolongation Cost Claims - An eye for detail
The strength of any claim lies in the attention to the detailed substantion.
| Causes of Lost Productivity
A loss of productivity can be successfully demonstrated and claimed if the causes are clearly identified.
| |||
Once a Contractor has secured an extension of time and relief from liquidated damages, thoughts will quickly turn to recovery of the costs incurred due to the delayed completion date...| more | It is acknowledged within the construction industry that demonstrating a loss of productivity on a project is one of the most difficult heads of claim to properly articulate...| more | |||
Demonstrating a Loss of Productivity Claim
There are many issues affecting productivity that are potentially outside the control of the contractor.
| Importance of Good Record Keeping
The conclusion has to be that any case is only as good as the evidence in support of it.
| |||
There are two industry recognised techniques for demonstrating, to varying degrees, loss of productivity, these being the total cost and theproductivity baseline methods, both of ...| more | It is however one thing for a Contractor to demonstrate that a failing of some sort on the part of the Employer has directly caused it to suffer a loss but quite another thing to prove...| more |
Supervision of the Works Guideline
According to FIDIC a Contractor shall give or provide all necessary supevision during the execution of the Works.
| Programme for the Works Guideline
The establishment and continual monitoring of a detailed, critical path method programme is essential for the...
| |||
In addition to the constant management and supervision of the Works, all significant types of works must also be under the close control of competent trade supervisors...| more | management of the Project.This will include a detailed Critical Path Method programme establishing key milestones and completion dates for the various sections of the Contractl...| more | |||
Clause 14 Programme Guideline
The Contractor is bound by the FIDIC Contract to submit the Clause 14 programme within 28 calendar days after...
| Monthly Progress Reports
FIDIC requires that the Contractor submit monthly updates of the Programme demonstrating progress to date.
| |||
This programme must cover all aspects of the design, approval, procurement, construction, installation, removal and commissioning of the temporary and permanent works...| more | The Contractor is generally required to attend monthly Progress Meetings with the Engineer to report the progress of the design, procurement and construction works...| more | |||
Extension of Time Claims
Claims and Delays are commonly associated with construction and its related activities.
| Method Statements Guideline
Method Statements describes how the Works are to be designed, procured and constructed
| |||
Most contractors are not legal experts and find themselves all too often in a situation where a delay has occurred whereby they did not have the necessary paperwork or records in place to make such a recovery ...| more | In addition to the above all hazardous work activities should be described by the issue of Detail Method Statement. As a general guideline each Method Statement should be structured and prepared in the following format...| more |
Project Specific Health and Safety Plan Guideline
Contractor increasingly required to demonstrate a positive attitude towards Health and Safety...
| Variations or Extra Work
Contractors are entitled to be paid for extra work required during the execution of the Contract
| |||
through the implementation of a preventive management style.The Health and Safety Plan should detail the following items and provisions to be implemented...| more | It has long been my view that the full cost of variations are generally not recovered by Contractors. When there is doubt as to whether an item is an extra or not...| more | |||
Format of Operation and Maintenance Manuals
The preparation and presentation of a well-prepared O&M manual is therefore an essential part...
| Business Letter Writing Fundamentals
The key to Good communication starts with Letter Etiquette.
| |||
of any building services installation contract. The final format of any O & M manual will be influenced by a number of factors. Generally the format of an Operating and Maintenance manual must be..| more | A good letter becomes a key element of your overall branding and market image. Learn more on how to create and maintain good construction letter writing principles...| more | |||
Application for Final Certificate
At the end of the Defects Liability Period you can apply for the Final Certificate..
| Monthly Cost Reporting Concept
Costs must always match the revenue that is being claimed...
| |||
In order for the Engineer to issue the Final Certificate the Contract requires that he has in possession or have received the following documents, certificates, material or clearances...| more | The document is divided into two main sections, namely, VALUE and COST, which enables the Quantity Surveyor to show the measured value to date ...| more |
Schedule of Area Measurement Formulae
Basic list of the most common area and perimeter formulas used in Construction...
| ||||
The list includes all common 2 dimensional shapes or plane figures detailing both the perimeter formula and area formula respectively...| more | ||||
Schedule of Volume Measurement Formulae
Basic list of the most common volume formulas used in Construction...
| ||||
The list includes all common 3 dimensional shapes or solid figures detailing both the volume formula and surface area formula respectively...| more | ||||
Change Management Schedule Benefits and uses
It is inevitable that a Contractor have to accommodate changes...
| ||||
The introduction of a change management schedule should not be seen as a “finger pointing” exercise. Its purpose is merely to manage a large...| more | ||||
No comments :